# Create downtime reasons

> Define planned and unplanned reasons to classify production stops.

**Downtime reasons** explain why an operation or group of operations stops. They can be planned, such as a break or shift change, or unplanned, such as a breakdown, missing materials, or a quality issue.

Recording the reason lets you analyze losses and recurring stops.

## Steps to follow

**Path:** **Production > Downtime reasons > +** (**New reason**)

**Name:** enter a short title that is easy to recognize on the pause screen. For example: `Lunch`, `Scheduled maintenance`, `Shift meeting`, or `Line cleaning`.

**Description (optional):** explain when to use the reason so the whole workshop follows the same criteria. For example: `30-minute break for the morning shift. Use only between 13:00 and 14:00.`

**Downtime type:** choose **Planned** or **Unplanned**. The form explains how each option affects OEE.

* **Planned:** for predictable stops in your usual operations, such as `Lunch`, `Shift change`, or `Scheduled cleaning`. Their duration is deducted from the workstation's scheduled time to calculate planned production time, so they do not reduce the workstation's availability or OEE.
* **Unplanned:** for unexpected events such as `Electrical fault`, `Raw material shortage`, or `Machine jam`. Their duration counts as lost production time, so they reduce availability and, with it, OEE.

OEE (%) = (availability (%) / 100) × (performance (%) / 100) × (quality (%) / 100) × 100.

Availability (%) is (actual operating time / (workstation scheduled time − planned stops that stopped it)) × 100. See [View OEE by workstation](https://docs.bold-factory.com/en/guides/manufacturing/view-oee-by-workstation.md) to review each indicator.