Prepare employee scheduling at three levels. First, define the work days for a single day. Then combine them into shifts. If needed, create holiday calendars for exceptional dates. A work day contains the working periods of a typical day. A shift repeats those work days in a cycle. A holiday calendar, formerly called a local calendar, overrides the pattern on dates such as public holidays, closures or days with special hours.
If your employees work the same hours as the plant, you do not need shifts or holiday calendars of their own. An employee without their own shift works the weekly schedule of the general calendar, and without their own holiday calendar follows its holidays. See Set plant working hours and holidays.

Before you start

You need permission to manage employee scheduling. Also decide:
  • which daily schedules repeat in your factory;
  • which fixed or rotating cycles each team uses;
  • which sites or areas share the same public holidays and closures.

Create work days

Path: People > Work days
1

Create a work day

Click + (New work day), to the right of the title, and enter a recognizable name, such as Morning, Night or Split day.
2

Add working periods

Click Add period and specify the Start time and End time. Add several periods to represent a split day without counting breaks between them as working time.
3

Configure overnight periods

Select Ends the next day when a period crosses midnight, such as 22:00 to 06:00.
4

Represent days off

Create a work day without working periods and give it a name such as Non-working day. You can use it in shifts and in each employee’s exceptions. Holidays do not need work days: you mark them directly as Closed or Special hours.

Build a shift

Path: People > Shifts
1

Create the shift

Click + (New shift), to the right of the title. Enter a name and add a description if it helps identify the cycle.
2

Add the first segment

Select a work day and specify how many consecutive days it should apply.
3

Complete the cycle

Click Add segment to add the following work days in order. Include segments with the Non-working day work day when the cycle includes days off.
4

Review the sequence

Check that the order and duration of the segments represent the whole cycle before creating the shift.
For a rotation of five mornings and two days off, add a segment with the Morning work day for 5 days and another with Non-working day for 2 days.

Add a holiday calendar

Path: Control panel > Plant > Calendar > Holidays Use a holiday calendar of their own when a group of employees must follow holidays different from those of the general calendar, for example those of another site or town. If two plants have different public holidays, create a holiday calendar for each. The holidays the whole plant shares go in the general calendar. See Set plant working hours and holidays.
1

Create the holiday calendar

Click + (New holiday calendar), to the right of the title. Add a name that identifies the site or area and a description if you need to explain its scope.
2

Open the holiday calendar

Open the created holiday calendar and navigate to the month you want to configure.
3

Mark each date

Click the day to open the Holiday on dialog with the date. Choose Closed or Special hours and, in that case, add its periods.
4

Save the date

Click Save. To remove a date, open it and click Remove holiday.

Next step

Once work days, shifts and calendars are ready, assign them to each employee.

Assign employee schedules

Assign a shift, holiday calendar, time zone and individual exceptions.