A production plan is a planning scenario. It copies open operations, resources and their availability, restrictions, dates and stock context to calculate a sequencing proposal. The plan does not change actual execution until you apply it.

Conceptual model

What they are for

Creation and updates

When you create a plan, Bold loads all active operations and orders, stations, tools and the available time of each station. The horizon starts at the current moment, or at the earliest planned start if earlier, and spans one year. You do not choose a subset of orders, dates or resources during creation. The two solving options let you choose the Solving mode when creating the plan. The application initially selects Basic (fast). Updating the plan copies current operational reality again. Later changes to orders, resources, calendars, maintenance work orders or materials do not appear until you update it again.

Resource availability

A station without its own calendar inherits the calendar of its line or area, up to the general calendar. If the general calendar has no working period in the horizon, Bold cannot create or update the plan. See Plant calendar.

Solve and apply

Solving calculates a proposal. You can also request automatic application if the calculation finds a solution. The Solve dialog initially selects Basic (fast). If you integrate through the API and omit mode when creating and solving a plan or calling the solve operation, the server uses Advanced (optimized). When applied, Bold updates the target date of included open operations. For Pending or Planned operations, it also updates the selected station and tool. It does not create employee assignments or modify finished or canceled operations.

Due date and safety margin

The plan tries to finish each MO by the end of its due day, at 23:59 in the company’s time zone. The time of day of the due date does not move that limit earlier. The Planning safety margin in Configure the company moves the limit that many days earlier, to leave time to prepare the material: Both solving modes plan against that limit. Basic mode finishes MOs with a firm date just in time for the limit, and advanced mode treats missing the margin the same as a delay. The MO’s due date does not change. A change to the margin applies when you update the plan.

Continuity

The plan respects the continuity of each manufacturing order:
  • Operations with the same workstation continuity are planned on one workstation, which stays reserved from the start of the first one to the end of the last one.
  • Operations with the same tool continuity use one tool, reserved in the same way.
  • Operations with the same line continuity are planned in one line, each on its own workstation. The line is not reserved, so other orders can use it in between.
An operation that is started, finished or locked in the plan keeps its resource, and the rest of its group follows it. If no resource is common to the whole group, each operation is planned on its own. Operations without a continuity key are planned on their own even when they use the same tool. While the reservation lasts, no other operation can use that workstation or tool. If an operation of the same order needs it between two operations of the group, for example because its restrictions place it there, give it the group’s key too; otherwise the plan finds no solution.

Calculation statuses

Read Manufacturing statuses to distinguish plan statuses from actual execution statuses.
Solution found describes the calculation result. It does not mean actual operations are Planned with those dates and resources.

What it does not modify

A plan does not change finished or canceled operations or replace actual execution records. It works on the copy of open work available when it was created or updated.

Relationship with planning

Planning answers what is missing and when. The production plan answers how to fit manufacturing work into available resources and time slots.