Path: Smart Factory > Dashboards > Effectiveness by employee1. Choose the employee and period
Select the employee and start and end dates. Bold uses the employee’s schedule (personal schedule, local calendar, and shift) to determine when they should have worked.2. Read the timeline
Manufacturing operations, maintenance work orders, and warehouse loads and movements count as tasks. If the employee has several simultaneous tasks, their time is split equally among them.
3. Interpret indicators
Utilization
Utilization (%) = (Time worked within schedule / Scheduled time) * 100 A low value indicates scheduled time without recorded tasks: insufficient workload, waiting, stops, or unrecorded work.Efficiency
Efficiency (%) = (Earned standard time / Evaluated actual time) * 100- Earned standard time: theoretical time for produced units (good and rejected) according to operation steps, multiplied by the people required.
- Evaluated actual time: employee time on operations with theoretical time whose production has already been recorded.
Quality
Quality (%) = (Good units / Produced units) * 100, according to the employee’s share in each segment.Productivity over schedule
Productivity (%) = (Earned standard time / Scheduled time) * 100 Combines utilization and efficiency in one number.OLE
OLE (%) = (Utilization (%) / 100) × (Efficiency (%) / 100) × (Quality (%) / 100) × 1004. Review details
- By day: schedule, work within and outside schedule, idle time, utilization, and efficiency for each day.
- By operation: employee and team time, coworkers, evaluated and pending time, earned standard time, efficiency, and attributed units.
- Idle time: each interval without tasks within the schedule, with the pause reason when known.
Limitations
- Bold does not record clock-ins: idle time is scheduled time minus recorded work.
- Past days’ schedules are calculated using the current schedule configuration.
- Efficiency for earlier days can change when recording production for operations that remained open.