Define materials
Classify materials according to their role in the operation:- Raw materials (external inputs): materials entering the plant unprocessed, such as raw milk. Record them as inputs to the operation consuming them.
- Semi-finished items (work in progress): intermediate products that have completed a stage but still need further operations, such as table legs. Record them as inputs to the next operation.
- Co-products (simultaneous outputs): items obtained simultaneously in a process, such as cream and skimmed milk during centrifugation. Record them as outputs of the operation generating them.
1. Add the material
Item: select the raw material, semi-finished item, or co-product to incorporate into the recipe. Quantity/manufactured unit: define consumption per manufactured unit. Enter a number with a decimal point or a formula. Use Property and Order data, or type@, to insert numeric item properties or the MO quantity. Use Round to add round, ceil, or floor. Below the field, you can see whether the formula is valid. Bold substitutes each value when generating the MO. See recipe formulas.
Consumption moment: choose when consumption is recorded:
- At the end: the ingredient is fully consumed when the operation finishes.
- Every unit: consumption is calculated proportionally for each manufactured unit. This option is selected by default.
Example: cheese consumption per unit
- Item: select Grated mozzarella cheese from the dropdown.
- Quantity/manufactured unit: enter
0.15to indicate each pizza requires 0.15 kg or 150 g of cheese. - Consumption moment: choose Every unit. The system deducts 150 g of mozzarella each time the line finishes a pizza.
How an operation runs
1. Add instructions
Instructions describe what the operator should do within an operation. An instruction can be a one-off task, such as preparing a machine, or a repetitive action, such as checking each unit. Instructions belong to an operation and can run at the start, at the end, or according to the quantity produced, depending on their configuration. Name: write a short text starting with an action verb, such asClean the die, Pour the additive, or Die-cut the sheet.
How many times must this instruction be performed?
A manufacturing order can produce one unit or many. The execution moment indicates whether the instruction runs once or repeats according to quantity.
- At the start: for machine preparation, initial loading, or a preliminary check. For example:
Preheat the oven to 180 °C. - Every unit: for actions repeated with each unit produced. For example:
Check the unit weight.
- Technical and safety text: describe the procedure, machine parameters, or necessary warnings. For example:
Set the pressure to 4 bar. - Formatting: use bold, italic, Heading, and Subheading to structure text, and Link to add a link with its text.
- Files: use the paperclip to attach PDF drawings, technical data sheets, or reference photos.
- Item and order data: use Property or Order data, or type
@, to display values such as item length, requester, or MO quantity. - Formulas: use Formula to create a block replaced by a calculated result, such as
Prepare ceil(MO quantity / 12) boxes. Use Round to addround,ceil, orfloor.
0.5. Formulas are also supported.
Assign inspections
Inspections require the operator to record a check when starting or completing an operation, according to configuration. Use them to capture evidence, quality parameters, or validations that must be linked to the operation.1. Add an inspection
Click Add inspection and fill in these fields: Name: enter a short descriptive title, such asTemperature measurement or Visual seal inspection.
Instructions: explain how to perform the inspection. You can add text, use formulas, or attach drawings, reference photos, or PDF manuals.
Values to record: click Add value for each value the operator must record and choose its type: Number, Yes/no, Text, Photo, or File. Without values, the inspection is a confirmation that it was done. If you ask for a single value, its name is optional: leave it empty to give it the name of the inspection. Name it when the name adds something, such as the unit (Temperature (°C)).
Number of records: enter how many times the inspection must be done. It accepts formulas, such as ceil(Production order quantity / 500). Select Allow adding more to make it a minimum so the operator can add more records.
When is it required?: choose Before starting, Before finishing, or Optional — does not block the operation.
See Inspections and checks for how records and requirements affect the operation.