Skip to main content
Preventive maintenance defines rules to generate recurring work orders. The schedule is not the work order. The schedule indicates when a work order should be created, on which asset and with which initial information.

What a schedule defines

Generation policies

Use the policy according to the risk of duplicate work orders. Every occurrence can be useful for critical inspections. For repeatable low-urgency tasks, skipping while work is open may be better.

Relationship with work orders

When generated, the work order contains actual execution. Complete it with times, actions, materials and observations like any intervention. The schedule retains frequency and generation history. The work order retains what was done. Schedule details show related work orders, except canceled ones. If the main cause requires stopping the machine, the generated work order makes the workstation unavailable in production plans from its scheduled occurrence, for its theoretical time. See Work orders.

Owner

The schedule can assign an employee as the owner of the work orders it generates, whether on schedule or with Generate now. It is optional: without an owner, the work order takes the first employee who records time on it. If the employee is deleted, Bold removes them from the schedule and from the open work orders it generated. Completed and canceled work orders keep them.

Deleted assets and causes

A schedule can only use assets and causes that are not deleted. Bold checks this when you create it, update it, or enable it again.
  • If you delete the asset or the main cause, Bold disables the schedules that use it. To enable one again, first change its asset or cause.
  • If you delete an auxiliary cause, Bold removes it from the schedules that use it, which stay enabled.

Generate manually

You can create a work order immediately with Generate now, for example to bring an inspection forward.
  • It counts as a generation: increases the generated counter and updates the last generation.
  • It does not change the next planned generation.
  • It does not consider the generation policy.
  • It works even if the schedule is disabled, but not if deleted.
If the policy is Skip if there is an open work order, a manually generated work order that remains open also causes the next occurrence to be skipped.

If it does not generate a work order

Check these points when a preventive schedule does not create the expected work order:
  • the schedule is enabled;
  • there is a next generation date;
  • the asset and main cause have not been deleted: if they have, Bold disables the schedule;
  • the policy is not skipping the occurrence because a work order is already open;
  • the frequency and time zone match the actual working calendar.
If you use Skip if there is an open work order, close or cancel the previous work order before expecting another generation.